A High Court ruling has prompted NSW Resources to overhaul how native title is assessed for certain mining lease applications. Consultant Holly Hannon outlines the new Infrastructure Facility Process — what triggered it, who it applies to, and what it means for project timelines.
Read the full update
NSW Resources Department of Primary Industries and Regional Development ("Department") has adopted a distinct native title process, referred to as the "Infrastructure Facility Process", for mining lease applications for Ancillary Mining Activities ("AMA") only. Driven by the High Court's ruling in Harvey v Minister for Primary Industries and Resources [2024] HCA 1 ("Harvey"), this regulatory change effectively replaces the traditional Right to Negotiate ("RTN") process, and pivots to validation of the future act via section 24MD(6B) of the Native Title Act 1993 (Cth) ("NTA"). The Infrastructure Facility process introduces a new timeline and negotiation framework that project managers must now navigate.
Key takeaways
- The Infrastructure Facility process applies to the grant of mining leases for AMAs under the Mining Act 1992 (NSW), where the proposed acts align with the description of infrastructure facilities within the NTA (or the ordinary meaning of infrastructure facilities), and are for the sole purpose of the construction of such a facility.
- In NSW, the Department has introduced the Guideline: Application of the native title infrastructure facility process to mining leases for ancillary mining activities ("Guideline"), which has been released for industry to follow.
- Neither the Department nor an applicant can choose whether the Infrastructure Facility process or the RTN applies to a particular mining lease — if the mining lease meets the Infrastructure Facility criteria, the RTN cannot apply.
- Compared with the RTN, the initial notification period is shorter, and public advertising is removed. Unresolved objections may be escalated to the NSW Civil and Administrative Tribunal ("NCAT") after 8 months.
- If the Infrastructure Facility process is applied to the grant of a mining lease, it will likely apply to each renewal. It may also apply to a variation of a mining lease, including where a new right is created or an existing right is expanded.
Key facts
In Harvey, the High Court considered the validity of the grant of a mining lease to construct a dredge spoilage emplacement area at the McArthur River Mine project in the Northern Territory, as a result of required future act processes under section 24MD(6A) or section 24MD(6B) of the NTA. The High Court ruled that the grant of this mining lease was a future act within the meaning of an "infrastructure facility" under the NTA, and restricted its grant until processes under section 24MD(6B) of the NTA had been followed.
Section 24MD is part of the future acts regime of the NTA and is applicable to acts that pass "the freehold test" — if an act can be done on freehold land, then it can be done on land subject to native title. If section 24MD applies to a future act (such as the grant of a mineral lease), the native title holders must be afforded the same rights as freehold land owners.
Section 24MD(6B) provides additional rights of objection to mining activities that involve the creation or variation of a right to mine for the sole purpose of constructing mining infrastructure facilities. This includes notifying native title parties and observing a 2-month notification period during which the notified parties may object. Consultation and negotiation requirements following an objection must also be followed.
Importantly, the High Court confirmed that the definition of "Infrastructure Facility" in section 253 of the NTA is non-exhaustive. It extends beyond the expressly listed examples of roads, railways and ports to include facilities that meet the "ordinary meaning" of infrastructure, capturing ancillary support facilities such as workers' camps and administrative centres.
Key impacts
When considering whether the Infrastructure Facility process applies to a mining lease application, the Department will consider both the list of infrastructure facilities in section 253 of the NTA and the ordinary meaning of "infrastructure facilities". As a result of Harvey, the Guideline provides an extensive explanation of how most AMAs in NSW fall within this category.
The Infrastructure Facility process also has a number of key positive impacts on the timeline for native title processes affecting AMA approvals:
- Replaces public advertisement requirements with letters only to known native title parties;
- Shortens the native title party objection window from 4 months to 2 months;
- Removes the automatic negotiation process, which is only triggered if a native title party formally objects; and
- Caps the negotiation timeframe, requiring unresolved objections to be referred to NCAT after eight months.
For guidance on how the Infrastructure Facility process may affect your project, contact Hetherington.